Construction Machinery
Description
1.aac block making machine line (15 lines in India) preparation work
1)Land of 4 Acres is Required
2)Workshop area –approximately 30000 Sq Mt or 30000 sft
3)Total Plant area( construction area ) = 4500 Sq Mt or 45000 sft
4)Power connection needed – 500 KVA
5)Ideal manpower requirement is 40 nos. (Skilled – 10, semi skilled-10 and unskilled 20)
6)Skill division 40 workers = Main plant 2 nos of 10 hour shifts 15 people each + Boiler & Autoclave section 3 people in 3 shifts of 8 hours
7)Water requirement approximately 225 Tons per Day.
8)Fly Ash requirement approximately 225 Tons per day
9)The above power and plant calculations are based on Fly ash based AAC without Lime Crushing Unit and Ball mill for sand. If the process so require, we may add them at a later stage. But surely we give provisions for them at site right from installation stage
10)300 working days is considered in a year through 333 days a year is possible.
2.Autoclaved aerated concrete block production line suppliers detailed product description
1)Product weight is according to 600kg/m3 to control.
2)Annual capacity 200,000M3.
3)set raw material proportion: cement 6.5%, raw lime 23%, flyash 68%, gypsum 3%, aluminum paste powder 350g/M3.
4)water and material rate 0.631
5)one mould product 2.88M3
6)Casting slurry cycle time 5-6 minutes, cut cycle time 5 minutes.
7)casting slurry temperature 38-42 degree
8)body quiet stop. Time is 1.5-2.5housr, temperature 50-90 degree, after quiet stop body strength is 0.15-0.18Mpa
9 Steam curing cycle time, come in and out autoclave about 0.5hour, steam curing cycle time about is 6 hours/1.6Mpa, total 6.5 hours.
Read More
Previous
QT10-15 Full-automatic hydraulic pressure sand block making machine...
Dongyue Machinery Group Co.,Ltd
block making machine,brick machine,AAC block production line
Address: Dongyue Industry Area,
Linyi, Shandong
China, 276300
Tel: 00865398036228
Fax: 00865398025589